PLENTICORE - load/generation measurement
Installation position - home consumption (position 1)
Installation position - grid connection point (position 2 - standard)
Install the KOSTAL Smart Energy Meter in the house grid as shown.
INFO
The installation position of the KOSTAL Smart Energy Meter is set in the inverter.
Set up RS485 communication cable between inverter and KOSTAL Smart Energy Meter and connect.
Establish LAN connection from KOSTAL Smart Energy Meter and inverter to the Internet. As an option, the LAN connection from the inverter can also be connected directly to the KOSTAL Smart Energy Meter (switch function).
INFO
For details, see the inverter's operating manual and the KOSTAL Smart Energy Meter's installation instructions.
In this variant, the KOSTAL Smart Energy Meter runs as a slave and transmits data to the inverter.
The inverter does not have to be set up in the KOSTAL Smart Energy Meter because it is pre-configured to the Modbus RTU RS485 interface (A) as standard.
If changes are to be made to the settings, perform the following steps:
- Call up online interface of KOSTAL Smart Energy Meter Calling up user interface
- Call up Modbus configuration under Modbus settings.
- Select PIKO IQ/PLENTICORE from drop-down list
Press the Save button to adopt the settings.
INFO
When an inverter is selected, the predefined default values are adopted. These can be adapted if necessary.
Parameter | Value |
---|---|
Interface | RS485 A |
Mode | Slave |
Presetting | PIKO IQ/PLENTICORE |
Slave address | 1 |
Baud rate | 38400 |
Data bits | 8 |
Parity | None |
Stop bit | 2 |