Selecting phase usage
Select here the maximum number of phases you wish to use to charge your electric vehicle.
INFO

Damage to the electric vehicle is possible when switching phase usage
The Wallbox includes the option to switch phases whilst charging is in progress.
As some vehicles currently on the market are not compatible with a phase change whilst charging is in progress, automatic switching may, in isolated cases, cause significant damage to the vehicle.
Please check with your car manufacturer to confirm whether your vehicle supports this function. If not, please disconnect the vehicle from the Wallbox before a phase switch can be carried out.
When the phase is changed over while the charging plug is plugged into the vehicle, the charging process is always terminated before the phase is changed over. The charging process is interrupted for approximately 3 minutes.

- Standard (three-phase)
The three-phase electric vehicle can be charged with a power of between 4.1 - 11 kW. However, you can use this setting to charge all electric vehicles, no matter whether you want single-phase, two-phase or three-phase. The electric vehicle determines the maximum charging power. - Single-phase
The electric vehicle can be charged with a power of between 1.4 - 3.7 kW.
For three-phase electric vehicles, here you can change the number of phases for charging from three-phase to single-phase charging, which reduces the charging power to 1.4-3.7 kW. This is a good idea if you want to use Solar Pure Mode, for example, and do not have sufficient solar energy available (e.g. during spring or autumn). In this case, the vehicle can be charged with pure solar energy as of a surplus of 1.4 kW. - Automatic
With automatic phase switching, the wallbox automatically switches between single-phase (1.4–3.7 kW) and three-phase (4.1–11 kW) charging. This means the full charging range from 1.4 kW to 11 kW is available for charging the electric vehicle.
In Solar Pure charging mode, this means that, for example, if the surplus PV output is between 1.4 and 4.2 kW, a single-phase charging process can be started. If the surplus PV power rises above 4.6 kW during the charging process, the system automatically switches to three-phase charging. When the system switches phases, the active charging process is always interrupted first and only then restarted with the new phase setting.
Automatic phase switching procedure:
When charging begins, the system checks whether the surplus PV power is sufficient for three-phase charging. If this is the case, the charging process starts in three-phase mode. If the surplus PV power is insufficient, charging starts in single-phase mode. Every 15 minutes, the system checks whether it is possible to switch to three-phase charging. If so, the switch is made. For this to happen, the available charging current must be 7 per cent above the minimum charging current required for three-phase charging. This is usually 4.5 kW. If three-phase charging is no longer possible – for example, because the PV output is insufficient due to cloud cover – the system will attempt to switch to single-phase charging after 5 minutes. If the required surplus power is still insufficient for this, charging is paused.