Solar Plus Mode (Solar-optimised charging)
Solar-optimised charging is only possible in combination with a PV system and the KOSTAL Smart Energy Meter. The PV system supplies the energy needed to charge the electric vehicle.
If there is a PV surplus at the grid interconnection point, the amount drawn from the grid is replaced by the PV power or, if possible, increased to the PV surplus.
If desired, a minimum PV surplus power can also be defined here. This is the minimum level which must be present before charging is started at the power level defined by the customer. If the surplus power falls below the defined minimum value, charging is stopped again.
This function can be used to charge the electric vehicle in the evening, for example, when there is no longer enough PV energy available but the electric vehicle needs to be charged for the next morning.

1 | PV surplus This surplus can also be used to charge a battery. |
2 | Max. wallbox charging power 11 kW (3-phase). |
3 | Fixed minimum starting charging power. In this example, at 50% of the max. charging power of 11kW (for 3-phase connection with 3-phase vehicle = 5.5kW). |
4 | Set min. surplus power at the grid connection point before charging is started. In this example, 60 % of 5.5 kW = 3.3 kW. The additional charging power of 2.2 kW (5) is drawn from the public grid. |
5 | Charging electric vehicle from the public grid. In this example 2.2 kW. |
6 | Charging electric vehicle from PV surplus. |
7 | Electric vehicle charging time. |
8 | Home consumption of other devices - partly covered directly from PV. |
Set the initial charging power
1 | Setting the target initial charging power. |
2 | Slider for adjusting the ratio between solar energy used and electricity drawn from the grid. |
3 | Display of electric vehicle charging values. |
Setting the charging power
Min. | This determines and sets the minimum charging power of the connected electric vehicle (1-phase 1.4 kW / 3-phase 4.1 kW). |
50 | The charging power is set to 50 per cent of the electric vehicle’s maximum charging power (single-phase 1.85 kW / three-phase 5.5 kW). |
75% | The charging power is set to 75 per cent of the electric vehicle’s maximum charging power (single-phase 2.8 kW / three-phase 8.25 kW). |
Max. | In this case, the maximum charging power of the connected electric vehicle is determined and set (single-phase 3.7 kW / three-phase 11 kW). |
Setting the minimum solar surplus
In Solar Plus mode, the slider can be used to set the ratio between solar energy used and energy drawn from the grid.
Example: If 30% solar energy / 70% grid draw is set, at least 30% solar energy must be available before the charging process starts. The remaining energy is drawn from the grid. If the proportion of solar energy increases, the grid draw is reduced.
Display of charging values for 1-phase and 3-phase electric vehicles
The illustration at the bottom shows the setting in kW for 1-phase or 3-phase vehicles. If more solar power is generated than the min. set, the amount drawn from the grid is reduced by the corresponding proportion.
Prioritisation of loads and battery usage
Prioritisation
The priority of loads can be set using the arrow keys. The load with the highest priority is given preference. This means that if the wallbox is in first place, the PV energy generated is made available to the wallbox and, if battery use is activated, the battery is also used for charging.
If the battery is in first place, the PV energy generated is first used to charge the battery until it is full, and only then is it supplied to the device in second place.
Battery usage
If a battery is present in the home network, it is not normally used to charge the electric vehicle. The additional use of the battery can be configured via the switch. Depending on the inverter with a battery in the home network, this function may not be available in all modes.

‘Allow battery use’ enabled: In this case, the home battery is also used to charge the electric vehicle. This means that the battery is used to charge the electric vehicle until it reaches the minimum SOC.
Battery usage disabled: In this case, charging the electric vehicle from the home battery is prevented. The electric vehicle is charged only from other sources, e.g. the public grid and surplus PV.
INFO

Clouds/hysteresis for drawing power
If the necessary excess power is not available, charging is maintained for approx. 5 minutes at the minimum charging power to avoid unnecessary switching on and off. After the hysteresis time has elapsed, charging is interrupted and only resumed after a wait time of approx. 8 minutes.