Handover to the operator
Following successful installation and commissioning, all documents are to be handed over to the operator.
Instruct the operator in how to use the PV system and the inverter.
The operator must be made aware of the following points:
- Position and function of the DC switch
- Position and function of the AC line circuit breaker
- Procedure for disconnecting the device
- Safety when handling the device
- Appropriate procedure when checking and servicing the unit
- Meaning of the LEDs and the display messages
- Contact person in the event of a fault
- The provision of system and inspection documentation in accordance with DIN EN 62446 (VDE 0126-23) (optional).
As the installer and commissioning engineer, have the operator confirm the proper handover with their signature.
As the operator, have the installer and commissioning engineer confirm that the installation of the inverter and the PV system is safe and complies with standards with their signature.