Menu "Service – grid parameterization"

 

Level 1

Level 2

Level 3

Service menu

Parameterization report

Overview of parameters set in the inverter

Reactive power settings 5

Reactive power configuration

Start-up ramp 5

Configuration of start-up ramp if there is a start-up or grid error

LVRT/HVRT 5

LVRT/HVRT

P(f) 5

Configuration of power reduction in the case of overfrequency P(f)

P(U) 5

Configuration of power reduction in the case of overvoltage P(U)1

Settling time 5

Configuration of the settling time.

Setting the settling time with external control, reactive power or active power by means of ripple control receiver or Modbus

Grid and system protection 5

Grid and system protection.

Configuration of the grid and system protection: Voltage L-N, frequency, start-up voltage, start-up frequency, start-up waiting time for start, start-up waiting time for grid error

Grid and system protection self-test

Self-test for grid and system protection

Performs a self-test and outputs the result for it