Other battery settings

This menu option is not displayed on inverters that have been configured as MDC clients. Control is handled by the inverter that has been configured as the MDC host.

Parameter

Explanation

Storage of excess AC energy from local generation

If there is an additional AC energy source in the local house grid (e.g. an additional PV system or a combined heat and power unit), the AC energy generated can be stored in a battery connected to the PLENTICORE.

NOTE! The function can only be activated if the energy meter has been installed at the grid connection point (position 2).

Activated: The AC energy generated can be stored in the battery.

Deactivated: Extra generated AC energy is not stored in the battery.

Battery charging as of grid surplus of [W]

Enter a minimum grid surplus value as of which the battery is charged. (Default 50 W.)

Example: If a value of 50 W is set, the battery is charged when feed-in into the public grid (grid surplus) is more than 50 W. Charging to the battery is blocked if the value is below 50 W.